By the Apex Projects Co team · Published
The short answer
An easement is a strip of land on your title that gives council or a service authority access to drains, sewers or other services. Building over one, or within 1 m of a council drain, needs council consent before work starts.
How to check
Order your Certificate of Title and Plan of Subdivision from Landata. Easements are usually along the rear or side boundary.
What's likely to be approved
Cardinia Shire lists fencing, paths, eaves, earthworks and retaining walls running parallel to the easement as likely to be approved, where there's no impact on drainage. Permanent enclosed structures like brick garages are unlikely to be approved. Removable or lightweight structures may be considered case by case.
Timeframes
Frankston City Council aims to respond within 10 business days of payment. Work, including delivery of materials, must not start until consent is issued.
Common questions
Do I need consent to lay turf over an easement?
Cardinia says grass, synthetic turf and mulch don't need build-over-easement approval.
Sources
- Cardinia Shire — apply to build over an easement
- Frankston City — apply to build over an easement
- City of Casey — apply to build over an easement
General information only — rules change and vary by property. Confirm with your building surveyor or council before you build.